AQW 29890/22-27 Written question to the Minister of Education

To ask the Minister of Education to detail the minor capital works to take place in Lagan Valley, during the 2025-2026 financial year.

Asked by Michelle Guy MLA on 3 July 2025

  • Answered
  • Written
Tabled
3 July 2025
Answer due by
22 July 2025
Answered
16 July 202513 days after tabling
Department
Department of Education
Priority question
No

Answer

The table below shows the minor works projects which are currently being progressed for schools in Lagan Valley. The projects are at various stages and progression of these projects to construction will be subject to detailed design, statutory approvals, available capital budget and competing priorities. While these projects will be developed during the 2025-26 financial year, delivery of many of them are likely to span future financial years.

School NameScheme DetailCurrent status
Brookfield SchoolAdditional accommodation, nursery unitTo complete March 2026
Brookfield SchoolSept 26 accommodationTo complete August 2026
Carr Primary School, LisburnReplacement wastewater treatment plantTender returned 30/05/2025
Carr Primary School, LisburnSpecialist Provision AccommodationAwaiting direction from Children Young People Services (CYPS)
Downshire Primary School, HillsboroughBoundary Anomaly between School and Housing DevelopmentFeasibility and Business Case (BC) assessment ongoing
Dromore Central Primary SchoolTraffic Management Scheme /CarparkingTo complete 25 August 2025
Dromore High SchoolPupil toiletsTo complete October 2025
Fair Hill Primary School, DromaraSpecialist Provision Accommodation Phase 1Start on site 16 June 2025
Fair Hill Primary School, DromaraSpecialist Provision Accommodation Phase 2Extent of works to be confirmed
Knockmore Primary School, LisburnTraffic Management Scheme /CarparkingFeasibility and Business Case assessment ongoing
Laurelhill Community College, LisburnLobby securityTo complete Feb 2026
Laurelhill Community College, LisburnTwo additional modular classroomsBusiness Case approved June 2025
Lisburn Central Primary SchoolBoundary & Fencing issueFeasibility and business case assessment ongoing
Lisburn Central Primary SchoolSecurity/Safeguarding worksBusiness case approved 27 June 2025
Lisburn Central Primary SchoolSpecialist Provision AccommodationAwaiting direction for 2026 provision
Lisnagarvey High School, LisburnThree classroom modular accommodationCompleted 27/05/2025
Lisnagarvey High School, LisburnAdditional changing facilitiesCompleted 02/04/2025
Lisnagarvey High School, LisburnAccessibility amendments - pupil specificSite visit held end of May. Feasibility ongoing.
Parkview SchoolUrgent additional accommodationAwaiting Business Case approval
Parkview SchoolMapping exerciseFeasibility and business case assessment ongoing
Parkview SchoolRefurb of hydrotherapy poolFeasibility underway
Parkview SchoolSpecialist AccommodationFeasibility to be completed
Riverdale Primary SchoolSpecialist Provision AccommodationAwaiting direction for an estimated 2026 delivery
St Aloysius’ Primary School, LisburnStandalone nursery unitBusiness case approved. Design Team has been appointed
St Mary's Primary School, DerrymoreUrgent health and safety fencingScheme completed 20/05/2025
St Michael’s Primary School, FinnisPupil Specific DDA Scheme - Visual ImpairmentWorks programmed to be completed by September 2025.
St Patrick's Academy, LisburnFoyer SecurityBusiness Case approved however discussions ongoing in relation to scheme design
Tonagh Primary School, LisburnSpecialist Provision AccommodationAwaiting direction for an estimated 2026 delivery