AQW 26224/22-27 Written question to the First Minister and deputy First Minister
To ask the First Minister and deputy First Minister to detail the amount spent on the maintenance of the Maze Long Kesh site in each of the last five years.
Asked by Michelle Guy MLA on 28 April 2025
- Answered
- Written
- Tabled
- 28 April 2025
- Answer due by
- 14 May 2025
- Answered
- 13 May 202515 days after tabling
- Department
- The Executive Office
- Priority question
- No
Answer
The amount spent on maintenance of the Maze Long Kesh site in each of the last five years is set out in the table below. These figures relate to the entirety of the site, excluding the lands transferred to the Royal Ulster Agricultural Society.
| Year | Annual Total (£) |
| 2020 – 2021 | 91,796 |
| 2021 – 2022 | 138,012 |
| 2022 – 2023 | 153,520 |
| 2023 – 2024 | 144,505 |
| 2024 – 2025 * | 114,097 |
* Provisional figure – subject to audit